Problem
- Customer has already gone through 13 replacement attempts, all of which failed
- Order was placed at a fixed price
- The suppliers specified by the customer are to be integrated into the project as subcontractors
Contribution of ResultONE
- Project organization and close consultation with the customer
- Detailed planning, negotiation of technical and commercial milestones with the customer
- Drafting of appropriate contracts with the subcontractors
- Setup and management of the development team (onshore/offshore)
- Coordination of the test team
Outcome
- Business requirements were signed off on time
- Functional specification of agreed schedule provided in 2 languages and accepted
- Technical design, user stories and use cases drawn up
- Database design and migration concepts created and accepted
- Database migration accelerated from 2 months to 4 days
- Monthly software deliveries on the basis of agreed milestones are working
All commercial milestones have been met, all the way through to acceptance testing